Arevon is proud to be building the Bell Solar-plus-Storage Project, located in Shiawassee County, Michigan

Location

Here is a snapshot of the project:

Size

Size

80 megawatts (MWac)/104 MWdc of solar and 90 MW of energy storage

Location
Land Area

Land Area

Shiawassee County, Michigan

80 megawatts (MWac)/104 MWdc of solar and 90 MW of energy storage, the project will have a footprint of approximately 585 acres of land to locate solar panel arrays, an operations and maintenance building, inverters, and access roads. 

Investment

Investment

Millions of dollars in local estimated investment based off of 170 MWac

Power Generation

Power Generation

When operational, Bell Solar-plus-Storage will generate enough energy to power the equivalent of 28,000 Michigan homes annually

Project Life

Project Life

Once constructed, the project has a 35-year lifespan, and upon project completion, the project will be decommissioned in accordance with a decommissioning plan

Project Details

Project Benefits

Community Benefits

  • Will generate property and sales tax revenue for schools, first responders, and other local needs

  • Compensates landowners for land use providing stable income source for over 35 years

  • Contracts with local businesses and services

  • Does not place heavy burden on government-supported services like schools and roads

  • Results in secondary economic activity for local restaurants, hotels, and other retail and wholesale businesses

Power Benefits

  • Solar requires no fuel source such as natural gas and coal, the cost and transportation of which can be as much as 30% of a consumer’s electric bill

  • Will help Michigan meet its renewable energy carbon-free goals

Environmental Benefits

  • Produces energy with zero-emissions

  • Will help improve surface water quality with a reduction in local fertilizer and pesticide use

  • The pollinator-friendly environment under the panels allows for soil recovery and boosts local surrounding crop production

Timeline

2019

Arevon initiates development of Bell Solar-plus-Storage Project

2024-2025

Engineering and environmental studies start

2025-2026

Permitting and pre-construction activities

2027

Construction start

December 2027

Commercial operation of Bell Solar-plus-Storage Project

For more information, please visit our FAQ section